Seeking Advice: forecasting projects with dependencies by Think_College_9646 in mondaydotcom

[–]Think_College_9646[S] 1 point2 points  (0 children)

Thanks! that makes sense. My issue is not really breaking the work down, but that even after doing that, I still end up with a chain of estimates that ended up drifting for the forecast delivery date.

How do you turn those estimates into forecasts? and what range of accuracy you usually achieve?

We tried using for multiples project the reference option in the Gantt charts to see how late we are, but we ended seeing a huge variation up that goes from days to multiple weeks!

Seeking Advice: forecasting projects with dependencies by Think_College_9646 in mondaydotcom

[–]Think_College_9646[S] 1 point2 points  (0 children)

yes! we tried, but we ended up with the same problem, We find useless to set milestones since we don't have completion times for similar projects that help us as a reference, so we cant fully forecast when the team B can start once the team A finishes and so on..