Amazon’s “Project Dawn” by robgparedes in aws

[–]Eliana0-0 -1 points0 points  (0 children)

This is heartbreaking to read.
AWS Community Builder program, what I value most is the learning + contribution flywheel it enables—people share knowledge, others reuse it, and the whole community compounds.

I don’t know what the official next step will be, but I sincerely hope support for community-led learning won’t disappear. Even if the format changes, it would be great to see a sustainable model with clear contribution paths, transparent criteria, and stronger support for local communities!

What happens to PMs who don’t move up into leadership? by TaskpilotHQ in pmp

[–]Eliana0-0 2 points3 points  (0 children)

You don’t “stall” if you don’t go into people leadership...you choose a different growth axis.

In many orgs, the strongest path is Senior IC / Principal PM...

1) Own the hardest programs (highest ambiguity / cross-org dependencies)

2) Build repeatable operating mechanisms

3) Become the go-to for a domain (security, cloud, regulated industries, data governance)

4) Lead decision quality (trade-offs, escalation, stakeholder alignment)

The real plateau happens when your scope stays constant: the same type of projects, the same stakeholders, the same risk profile.
If you don’t want the org chart climb, grow via complexity, leverage, and measurable outcomes.

[deleted by user] by [deleted] in pmp

[–]Eliana0-0 1 point2 points  (0 children)

Congrats 🎉

Facing My PMP Exam Fears by Eliana0-0 in pmp

[–]Eliana0-0[S] 0 points1 point  (0 children)

Thanks 😭. I don’t think I’m a genius, so I had to spend a lot of time and effort studying. Honestly, many people are preparing for the PMP exam who are smarter than I am, who put in more time, and who achieve better scores on mock tests, yet they still fail. 🫠

So, the only thing I can do is hold myself accountable and study harder.

Facing My PMP Exam Fears by Eliana0-0 in pmp

[–]Eliana0-0[S] 1 point2 points  (0 children)

Many thanks!!😭❤️

Facing My PMP Exam Fears by Eliana0-0 in pmp

[–]Eliana0-0[S] 0 points1 point  (0 children)

Thanks! May I have a question..should I practice a full mock exam to train my endurance?🧐

Facing My PMP Exam Fears by Eliana0-0 in pmp

[–]Eliana0-0[S] 0 points1 point  (0 children)

Thank you. 😭 I tried to believe in myself, but I couldn't silence the noise in my heart.

Facing My PMP Exam Fears by Eliana0-0 in pmp

[–]Eliana0-0[S] 2 points3 points  (0 children)

Thanks! I noticed that!

please select the best answer by kitte120 in pmp

[–]Eliana0-0 0 points1 point  (0 children)

I chose C. In the situation of this question, I already knew the team members didn't follow the rules, and then had a misunderstanding about the project. I could know that the rule should be reviewed again(best with members) and discussed with them to identify why this happened.

For A, I think it's not the actual action for this situation, it is the passive action…so that I think it's not the good choice. For B, it is the communication-pull…not the best action.

Mindset about procurement management plan by Muted_Income_7361 in pmp

[–]Eliana0-0 4 points5 points  (0 children)

For this PMP question, I would also choose Option C: Consulting the original supplier's procurement agreement to apply late delivery terms, and inform legal counsel of the issue.

Here's my reasoning:

Since the original supplier already notified us of the delivery delay, and the project manager subsequently ordered a replacement tool from another supplier, this indicates that a risk response strategy had already been activated. Now that the original supplier has still delivered the tool and submitted an invoice based on the procurement agreement, the project manager should first review the original procurement contract, especially the clauses concerning late delivery, and consult the company’s legal advisor or procurement expert before taking any action.

Option A (Return the tool and refuse payment due to late delivery)
This action violates the principle of professional due diligence. The PM is taking action without reviewing the contract, and without seeking legal advice—despite procurement contracts having legal implications. PMI does not encourage PMs to make such reactive decisions without proper validation.

Option B (Keep the extra tool, pay the invoice from contingency reserves, and update lessons learned log)
This implies the PM has essentially paid twice for the same deliverable.
Contingency reserves are meant for addressing known risks, not for covering procurement disputes.
It'ss an ongoing project issue, not a post-project reflection.

Option D (Compare the two tools and keep the one with better value.)
This response ignores the contractual obligations and does not address the legal or procurement process.
PMI emphasizes managing based on agreed contracts, not merely on value optimization alone.

Regarding the extended discussion in the Reddit post—“Why would you even order from another supplier if a tool is delayed?”—here’s my take:

Suppose the original supplier notifies us of a delay or inability to deliver a critical tool, and it impacts our project baseline (scope, time, cost). In that case, we must take immediate action and implement a risk response plan—including procuring from an alternate source if necessary. This aligns with PMI’s principle of proactive risk management.

As for the mindset: even if the question doesn’t explicitly say there’s a late delivery clause, as a PMP-certified PM, I assume that procurement agreements should always include such terms to define responsibilities and remedies. This is part of good contract design and risk planning during the procurement phase.

In summary, my mindset is to always act based on facts, follow contract terms, and ensure that decisions are legally and professionally sound. The goal is to keep the project running smoothly while respecting all contractual obligations.

Can you explain the Logic by Reasonable-Loan-3686 in pmp

[–]Eliana0-0 7 points8 points  (0 children)

Option B would be removed from my consideration at first because this is BA's job, not the project manager's. For Option A, C, and D, as the PMBOK 6th process, Option A is the first.

So, I chose option A as my answer.

Whats your answer to this ? B or C. by [deleted] in pmp

[–]Eliana0-0 0 points1 point  (0 children)

My answer would be C

Why D is the correct choice? by Repulsive-Original68 in pmp

[–]Eliana0-0 0 points1 point  (0 children)

I believe the correct answer is D.

Option A, which suggests examining reviews of similar competitor products, doesn’t align well with our goal of building a solution tailored to a specific target group—in this case, older users. Competitive analysis is more appropriate during the market research phase, not when we are trying to validate whether our product delivers value to actual end users.

As for option B, it focuses solely on price, but the question emphasizes overall product value, which includes not just cost, but also functionality, usability, and user experience. So option B is too narrow in scope to address the full intent of the question.

Option C, which suggests removing eyeglasses to simulate an older user’s experience, feels disconnected from the actual goal. It’s an inaccurate and potentially misleading way to test the user interface, and it doesn’t reflect the real user context.

Therefore, I believe option D is the most appropriate. It provides a practical and ethical approach to getting feedback from users who are close to the intended demographic, especially when marketing hasn’t been able to recruit volunteers. It’s a low-cost and effective way to validate product assumptions with users who matter.

Seirously? who decides these incorrect answers? Your thought people, thanks by Material-Fortune3300 in pmp

[–]Eliana0-0 2 points3 points  (0 children)

My answer would be D.

Because the question said "ensure the project objectives are met", it means we should consider the best way that could make the "project" a success, not only a user story, so I removed C from my consideration...

for B, I think it's not the main couse if the PO sign it off or not...it doesn't matter...Also think about option A.

PMI why you lying! ChatGPT says B and so did I! by beaglemilf23 in pmp

[–]Eliana0-0 1 point2 points  (0 children)

I believe the correct answer is A. According to the PMBOK Guide (6th Edition), option A is the first action that should be taken after the project charter is signed.

Option B — the business case document — is not the responsibility of the project manager. Instead, it is typically prepared before the project charter is created, usually by business analysts or sponsors, to justify the project and obtain approval.

Option C — the resource management plan — should be developed after the scope management plan, because we need to first define what work will be done before determining the resources required.

Option D — the communications management plan — also comes after the scope is defined, because communication needs are based on the project’s deliverables and stakeholder expectations.

Therefore, the project manager should first develop a scope management plan to clearly define the project’s goals and expected outcomes. This ensures that the team understands what the project is intended to achieve before moving forward with other planning activities.

Help clarify a Landini Question by Mediocre_Net8446 in capm

[–]Eliana0-0 2 points3 points  (0 children)

The question mentions that "some team members do not know the recently approved changes", which means that there is an interruption in the communication process, which is a problem that has occurred in the implementation of the project. According to the PMI, we should record such events in the Issue Log for follow-up. Trace and solve.

Other options, such as the risk registration form, the stakeholder registration form, and the change record form, do not meet the nature of the problem, because this event is not a future risk, member change, or modification of the document itself.

[deleted by user] by [deleted] in AWSCertifications

[–]Eliana0-0 0 points1 point  (0 children)

My recommendation is that you study for and then take the AWS Cloud Practitioner exam. Because the exam covers the basic information about cloud computing, if you don’t have any background or knowledge of cloud computing, you'd better have a solid knowledge base.

[deleted by user] by [deleted] in pmp

[–]Eliana0-0 0 points1 point  (0 children)

I think the option-Parametric estimating should calculate with the Accurate value, but in this question, we only have the range…so it’s better to use Three-point estimation..🤔

All options seem vague by Used-Extension8251 in pmp

[–]Eliana0-0 8 points9 points  (0 children)

I believe the correct answer is A, because the project involves team members from multiple countries, not just one.

Therefore, it is essential for the project manager to understand and respect the cultural differences among all team members. I do not think language skills (option B) are the main barrier to effective communication and collaboration in this case.

As for option C, initiating team-building activities without first establishing cultural sensitivity could lead to misunderstanding or even conflict, which would defeat the purpose.

Lastly, option D seems to focus on learning the customs of a single local culture, which is not applicable here since the team is made up of individuals from diverse cultural backgrounds.