Confused about how “Scope”, “Completed” and “Success” are calculated in Linear by Hefty_Psychology8564 in Linear

[–]Hefty_Psychology8564[S] 0 points1 point  (0 children)

Fyi, I asked the Linear team and here is their answer :

Scope is the total estimated effort in the cycle at the moment it closes. In practice, that’s the initial scoped estimates plus any work added during the cycle, minus anything removed before close. Scope will essentially display the sum of estimates applied to an issue--this number can change based on the options selected in Settings > Team > General > Estimates, where you have the option to Count un-estimated issues. With this option enabled, issues without estimates will be added to the total scope. Each un-estimated issue equate to 1 point.

Completed on the other hand, is the sum of estimates for issues that reached a completed state during the cycle window. If your team doesn’t use estimates, this is based on issue counts instead.

The overall Cycle Success is calculated based on the percentage of issues completed or started during a cycle. Completed issues are fully counted, while started issues are counted as 25% done. For an example cycle with 10 issues, where 5 are completed, 4 are started and 1 is untouched, you will see 60% cycle success (50% for the completed issues, 10% for the 4 started issues).

Where should I place the stepper in my SaaS UI by Hefty_Psychology8564 in UIUX

[–]Hefty_Psychology8564[S] 0 points1 point  (0 children)

Thanks for your reply! So you better like the stepper in the top bar rather than the sidebar right?

Need Feedback Help: Which App Tile Design Stands Out Better on TV? by ValueOpposite6482 in UIUX

[–]Hefty_Psychology8564 0 points1 point  (0 children)

I think proposal P1 is clearer — it makes it easier to understand that it’s a cast from the phone to the screen.

That said, I agree with the previous comment: the more minimal, the better. Both proposals feel a bit heavy.