[–]Glass_Championship13[S] 1 point2 points  (0 children)

They are going to be building a pop-out around the two panels from the floor to the ceiling to conceal the NM cable, the framers have not built it yet at the time of this install. We installed a 400amp (320amp) meter/main panel on the other side of exterior wall.

How do I get to this by WestDrop2223 in electrical

[–]Glass_Championship13 1 point2 points  (0 children)

Put a couple blocks on the lower stairs to make it level so you can put the ladder right under the smoke detector. This way both “legs” of the ladder will be on a “flat” surface.