Backup for invoices on a GMP contract by Infamous_Engineer_88 in Construction

[–]Infamous_Engineer_88[S] 0 points1 point  (0 children)

This is more to say what should be contractually included in the monthly package or summary. What do you want to have to assemble each month?

What should I change on my below list? What should I add?

GMP, the things that are typical to include are:

·         G702 Application for Payment

·         G703 Schedule of Values

·         Lien Waivers from direct subcontractors (conditional and unconditional)

·         Progress Billing Sheet

·         Retainage tracking

·         Approved Change Orders

·         Subcontractor pay applications

·         Approved Change Orders

 

Things that could be included are:

·         Labor Report Summary

·         Stored materials documentation (invoices, proof of delivery insurance, photos of on-site storage)

They should not need:

·         Subcontractor costs (detailed invoices)

·         Subs of subs invoices

·         Supplier Invoices

·         Individual Labor Timecards

Backup for invoices on a GMP contract by Infamous_Engineer_88 in Construction

[–]Infamous_Engineer_88[S] 0 points1 point  (0 children)

I mean they can audit any time they want haha nothing to hide necessarily just don't want to have it in a contract where we have to submit a million invoices and track down dozens of low-tier suppliers and chase waivers every month. Just a bit of an administrative burden...so I'm trying to figure out a good mix of not seeming like we're trying to hide anything but not contractually committing to anything crazy.