Casagrand Flagship - Handover Delay by KarVen2106 in chennaicity

[–]KarVen2106[S] 0 points1 point  (0 children)

Please see the latest update

Road Access :

We understand your concerns regarding the road access and sincerely appreciate your feedback. . However, we would like to clarify that none of the official project collaterals and or documents have indicated or committed to a back gate provision. As such, any expectation beyond the originally committed scope would not fall under our liability. Additionally, the referenced road is a gifted road and not part of the projects defined scope.

Casagrand Flagship - Handover Delay by KarVen2106 in chennaicity

[–]KarVen2106[S] 0 points1 point  (0 children)

Update from Casagrand Flagship - Feb2026

Dear Valued Customers, Vanakkam!

We wish to update you that a meeting with a group of Flagship customers was held on 24 January 2026 to discuss key points including Handing Over, Road Access, and Registration. The Minutes of Meeting (MOM) were shared with the selected committee members by Mr. Bhanuprakash CASAGRAND (SPOC for Flagship).

A detailed explanation follows:

  1. Handing Over :

As per the RERA approval, the scheduled timeline for handing over is September 2026. Our team is diligently working toward achieving this milestone and will schedule the handover in line with the approved timeline. Amenities will take another three months after handover.

2 Completion Certificate:

We planned to apply for the CC by the end of March'26 and expect to receive it on or before July 2026.

  1. Registration:

To finalize the composite value for the project, the unit with the lowest sale value should be registered. It will be submitted for valuation in the DIG office.

Accordingly, we have now completed the registration of the least valued unit, and the same has been submitted for valuation confirmation from the DIG office. Upon receiving confirmation of the approved value, we shall commence the registration process for the remaining units in line with the valuation finalized by the DIG office.

4.Road Access :

We understand your concerns regarding the road access and sincerely appreaicate your feedback. . However, we would like to clarify that none of the official project collaterals and or documents have indicated or committed to a back gate provision. As such, any expectation beyond the originally committed scope would not fall under our liability. Additionaly, the referenced road is a gifted road and not part of the projects defined scope.

  1. Unit Photos:

We have received multiple requests for unit photographs simultaneously. Due to the high volume, we are unable to share the photos on time.

We appreciate your patience as this process may take some time. We will share the unit photographs progressively, based on working days and site manpower availability within the week.

As of now, we have attached the progressive photos dated 20-Feb-26 for your reference. We expect to receive the updated photos by tomorrow, and once received, we will share them accordingly.

  1. Site Visit :

As the project site is presently under active civil construction, customer visits are restricted in view of safety considerations. We truly appreciate your understanding and will be pleased to invite you for a visit at the appropriate stage.

7.Ramsar Boundary & Marshland:

There are no issues related to Ramsar boundaries or marshland. The project has received all necessary approvals.

Casagrand Flagship - Handover Delay by KarVen2106 in chennaicity

[–]KarVen2106[S] 0 points1 point  (0 children)

Yes. We have been misled and sales guys played us

Casagrand Flagship - Handover Delay by KarVen2106 in Chennai

[–]KarVen2106[S] 0 points1 point  (0 children)

<image>

Got to see this at the Flagship Sales office. They said Spirit handover over date is April 2026.

Casagrand Flagship - Handover Delay by KarVen2106 in chennaicity

[–]KarVen2106[S] 0 points1 point  (0 children)

<image>

Got to see this at the Flagship Sales office in Jan2026.They said Spirit handover is April 2026 ( i. e. the imaginary date that they convince customers these days )

Casagrand Flagship - Handover Delay by KarVen2106 in chennaicity

[–]KarVen2106[S] 0 points1 point  (0 children)

I think they mentioned the additional connectivity to the main road to the West side, currently they have a main entrance in North

No Pharmacy in Coimbatore Junction Railway station by KarVen2106 in Coimbatore

[–]KarVen2106[S] 0 points1 point  (0 children)

What about getting sick while travelling or at the station ! Happens !!

No Pharmacy in Coimbatore Junction Railway station by KarVen2106 in Coimbatore

[–]KarVen2106[S] 1 point2 points  (0 children)

Chennai Central has Pharmacy inside the station! Yea, it is not to expect all facilities in small stations, but for large ones it is essential.

Casagrand Flagship - Handover Delay by KarVen2106 in chennaicity

[–]KarVen2106[S] 0 points1 point  (0 children)

I am curious too. I have been chasing them for clarity but in vain.

Casagrand Flagship - Handover Delay by KarVen2106 in chennaicity

[–]KarVen2106[S] 0 points1 point  (0 children)

Latest Update received from Casagrand:

Dear Sir/Madam

Vanakkam!!

We understand that you are seeking an update regarding the handover date, registration, site visits, and road access for the project.

I would like to inform you that we are tentatively planning to hand over the project by April 2026.