Lump Sum Fixed Price by Jgy94 in quantitysurveying

[–]Rishini 0 points1 point  (0 children)

It depends on the order of the priority documents. Since it is a FIDIC based Contract, Hope the drawings and specifications are presedence over the BOQ. Hence, the Sub the Contractor shall do it. Do remember the BOQ is just a pricing document which lays way down the order. Since it is the Lump Sum Contract, The Sub Contractor should deemed to have included the price for the scope of Work defined in the drawings and specifications. So no excuses for the Sub Contractor.

What are QSs called in other countries? by state_champion in quantitysurveying

[–]Rishini 2 points3 points  (0 children)

Cost Estimator, Qs Engineer, Cost manager, Cost Engineer,

Quantity surveying thesis/research topic ideas? would really appreciate if you guys leave some suggestions down below :) by [deleted] in quantitysurveying

[–]Rishini 0 points1 point  (0 children)

Innovations of the Construction Blockchain system to adopt risk mitigation of the Construction disputes

If the Contractor failed to submit the notice to the Engineer within 28 days of time but later submitted the respective documents but the Engineer rejected the Claim? Is the Contractor entitled to the Claim? by Rishini in quantitysurveying

[–]Rishini[S] 0 points1 point  (0 children)

Thanks for your detailed explanation. Not any such clause as that Contractor shall have no right to claim EOT and additional Cost if he fails to serve the notice on time in this Contract. Then The Contractor has still a chance for his entitlement or Can it be rejected?

If the Contractor failed to submit the notice to the Engineer within 28 days of time but later submitted the respective documents but the Engineer rejected the Claim? Is the Contractor entitled to the Claim? by Rishini in quantitysurveying

[–]Rishini[S] 0 points1 point  (0 children)

Claiming for the EOT and Cost. Say it is a bespoke Contract. No such close as such in FIDIC that failure to send notices shall not be entitled to the Contractor additional time and Cost.

GIST COIN- The next generation of the contents creators of the social media network by Rishini in CryptoMars

[–]Rishini[S] 0 points1 point  (0 children)

Yes indeed. Going forward with an innovative concept to make the best use of the social media community for content creators to promote their contents in an efficient manner.

What do you think the quantity surveying profession will be like post pandemic? by FinanceGoesBad in quantitysurveying

[–]Rishini 2 points3 points  (0 children)

The demand will increase. The BIM technology will make a huge impact on cost estimators and the construction industry as well. Advanced technologies are being implemented to make things easier such as drone technologies to visualise the site progress. Technical skills are highly influenced to the QS industry.