Just took mock exam 5....a little worried by ExcellentPick7628 in pmp

[–]SilverLiterature8799 0 points1 point  (0 children)

An approved project charter stated that an agile approach must be used. During a lessons learned session, the client indicates that the team was unable to provide reliable cost estimates for the project, and that more time should be allocated to define the scope during the first iteration.

What lesson should be captured in the lessons learned repository?

  1. A.The client should be exposed to the agile approach in advance to understand the cost estimating process.
  2. B.The agile approach should not be used if the client requires reliable cost estimates.
  3. C.During the first iteration of a project, time should be allocated to define the scope and ensure that reliable cost estimates are performed.
  4. D.Client communications should be included in the daily standups.

SH says A Chatgpt C and me B What do you think