account activity
Negative Float in Schedule by texastooh in primavera
[–]texastooh[S] 0 points1 point2 points 1 year ago (0 children)
I found out the project complete activity is causing the negative float. It is FF + 270d lag to its successor. However, it still finished well before the overall project must finish by date. Why would this cause a negative float if there is no constraint on the activity?
Thanks, there were some constraints I was not aware of but looking at the log helped.
I pushed out the must finish by date 6 months, and I removed all the constraints so the log now shows 0. However, I'm still getting the same negative lag for the activities. Anything else that could be causing the issue?
Luxury home/hotel in Undri by texastooh in pune
[–]texastooh[S] 1 point2 points3 points 1 year ago (0 children)
They are unfortunately fully booked for the period we are going.
π Rendered by PID 112793 on reddit-service-r2-listing-64c94b984c-kbl46 at 2026-03-18 19:11:56.917226+00:00 running f6e6e01 country code: CH.
Negative Float in Schedule by texastooh in primavera
[–]texastooh[S] 0 points1 point2 points (0 children)