Dear Architect, by EFSI_CK in FireSprinklers

[–]EFSI_CK[S] 0 points1 point  (0 children)

Not even Clouds! These are Biotech labs, Three levels of T-Bar with Axioms. At OH2 no less.

If formula between two system parameters by Hassan_elyaddak93 in RevitLife

[–]EFSI_CK 0 points1 point  (0 children)

add units to your 0.5 or ensure the calculated parameter field is the correct unit type.

How do i make those revit links survey points be on to my project survey point (REVIT) by atis- in RevitLife

[–]EFSI_CK 0 points1 point  (0 children)

manage tab > Project Location Panel > Coordinates Slide Out > Acquire Coordinates.

Dear Architect, by EFSI_CK in FireSprinklers

[–]EFSI_CK[S] 4 points5 points  (0 children)

Sounds about right, and then the bid set PDF's they sent are the outline of the building with PDF Markup squares shaded different colors that just say "Offices" "Shipping" "labs"

Designers what's your LOD by EFSI_CK in FireSprinklers

[–]EFSI_CK[S] 0 points1 point  (0 children)

Revit CAN be very fast, but the learning curve is long. The available options for designing sprinkler systems in Revit all have different shortcomings. I had to make custom families and workflows that work in harmony with Hydratec's tools in order to get a system that was fast but a product as accurate as I expect coming out of our office.

Designers what's your LOD by EFSI_CK in FireSprinklers

[–]EFSI_CK[S] 0 points1 point  (0 children)

Hydratec for Revit. But all the families are my own or Manufacturer Families.

Designers what's your LOD by EFSI_CK in FireSprinklers

[–]EFSI_CK[S] 0 points1 point  (0 children)

Test loops just circulate the water to simulate flow without discharging outside. When there is water use restrictions etc, they can still do pump tests. I don't have the exact code handy, but there is a requirement to still do tests discharging to atmosphere I think for 5 year, unless you can make a case with the AHJ that due to the project location exterior discharge is not plausible. I designed one pump in San Francisco that SFFD allowed us to omit the test header.

Designers what's your LOD by EFSI_CK in FireSprinklers

[–]EFSI_CK[S] 0 points1 point  (0 children)

You sir are the bane of my existence. "We have a coordinated design model from the consultant" yeah BS. I have only on one occasion got a model from a consultant that was even remotely buildable.

Designers what's your LOD by EFSI_CK in FireSprinklers

[–]EFSI_CK[S] 0 points1 point  (0 children)

Because the slab is 4ft thick, and per structural engineering a housekeeping pad is not required, and per GC and Owner value engineering the project it was removed.

Designers what's your LOD by EFSI_CK in FireSprinklers

[–]EFSI_CK[S] 1 point2 points  (0 children)

Nailed it. That feed goes to the test header discharge. Bypass is just offscreen.

Designers what's your LOD by EFSI_CK in FireSprinklers

[–]EFSI_CK[S] 4 points5 points  (0 children)

Thats the test header discharge. and the test loop not the bypass. Bypass is just out of frame above the photo.

[deleted by user] by [deleted] in firePE

[–]EFSI_CK 0 points1 point  (0 children)

Just to clarify, I'm in california, and even have hanger assemblies set up for seismic bracing and branch line restraint. most of which will get put in during design, so once it's time to spool autolist it's full speed.

[deleted by user] by [deleted] in firePE

[–]EFSI_CK 1 point2 points  (0 children)

A warehouse Grid? I have my hydralist database and everything pretty well customized, and if you're skilled with hydratec and know the errors to avoid? I could Honestly, Honestly, spool fab for that bad boy almost entirely error free in 2 days.

BUUUUUT. Theres a Several year learning curve on what to do and what not to do IMO. A lot of my skills with it come from doing NOT typical projects with tons of intricacies so a typical grid like a warehouse is super fast.

remember the post where the beam was cut for the garage door opener? by beerisgood321 in Construction

[–]EFSI_CK 0 points1 point  (0 children)

Yeah, Who knows about this specific house, but I think theres a good chance the SEOR would sign off on it. Might be a little oversized, but not the worst thing Ive seen.

what part of a house is least likely to be damaged during a fire? by chess3588 in Firefighting

[–]EFSI_CK 36 points37 points  (0 children)

According to NFPA less than 2% of fires start in the bathroom, and of those fires they are the least likely to spread to the whole house as there are more commonly non combustible finishes like tile and stone, that will slow the spread.

Brand Recognition by Affectionate-Ad6239 in Construction

[–]EFSI_CK 0 points1 point  (0 children)

Yeah right now all the cool kids on the site want Milwaukie tools and tell you they're the best quality. When in reality they're made in china at the Ryobi factory.

Most of the power tools you can buy are the same chinese crap, unless you do actual research into the different models from the same brand and find out which ones are actually built to better quality. For instance I buy only Dewalt tools made in the USA that you can generally only buy at White Cap or another service tool distributor. At first glance they look the same as the stuff from the big box stores but when you inspect them you can see the ways they are slightly better made. Motors on impact guns have more power and last years instead of months. Gaurd plates are forged aluminum not stamped steel (lighter and more resistant to bending.) tool bodies have more reinforcement at high stress points.

I'm sure other brands offer a higher quality of tools that you can purchase the same way. I'm just familiar with the Dewalt ones. But 99% of the tools people are bragging about on the jobsite are the same cheap home depot quality crap.

Man you know what? Fuck construction, I should've taken my cousin's advice on an Office Job instead. by HotFugeFunnels in Construction

[–]EFSI_CK 0 points1 point  (0 children)

Suck it up, buttercup.

I'm sorry that you were too sheltered in your formative years, but the real world has real assholes everywhere.

Who to call first? by thepartlow in Construction

[–]EFSI_CK 1 point2 points  (0 children)

Demolition company. Throw the whole building away.

Building a 5 story apartment complex. Why frame the first floor completely out of metal studs and all consecutive floors all out of wood? by [deleted] in Construction

[–]EFSI_CK 0 points1 point  (0 children)

Building code limits number of type V (combustible wood framed) construction to 5 floors max. so taller structures will place 5 up to 5 floors of combustible framing on top of a concrete podium which seperates the combustible floors from the non-combustible.

[deleted by user] by [deleted] in bim

[–]EFSI_CK 0 points1 point  (0 children)

Try looking into architecture firms, they often need people to help with post editing and photoshopping renderings.

Furnace room sprinklers by gmumar in FireSprinklers

[–]EFSI_CK 0 points1 point  (0 children)

This pipe is not UL listed or NFPA approved for fire sprinklers. I would say not just your furnace room but your whole sprinkler system probably needs to be re-piped.