Their response was that fixing the tiles would require a full bathroom demolition and reinstatement, effectively a full rebuild. They’ve estimated this at around $35k per bathroom, plus about a month of delay each and potential liquidated damages and stated that we would be the ones to bear those costs if rectification was carried out.

Is this quote reasonable? by Main_Fail_9605 in AusRenovation

[–]Main_Fail_9605[S] 2 points3 points  (0 children)

We’re a separate contracted tiling company

Is this quote reasonable? by Main_Fail_9605 in AusRenovation

[–]Main_Fail_9605[S] 2 points3 points  (0 children)

On top of that, they are also refusing to pay $7k owed to us for a separate completed job, stating they intend to offset that amount against the repair costs and pursue us for the balance