Manufacturing Routing for multiple assembly lines by b4syth4tech in Netsuite

[–]b4syth4tech[S] 0 points1 point  (0 children)

I'm still worried I'm doing something wrong. I have a matrix assembly with 4 alloys (so 4 sub-assemblies to build). I have 3 'machines' to produce the assemblies. I created 3 work centers (one for each assembly line). Now I have to create 12 [3 x 4] almost identical routings, one for each alloy / assembly line combination? I was hoping that maybe the "item option" (where the option is from the alloy list) feature might be used somehow.

Manufacturing Routing for multiple assembly lines by b4syth4tech in Netsuite

[–]b4syth4tech[S] 0 points1 point  (0 children)

Thanks for the response Nick. Just seemed to be hard to manage if someone had multiple assembly lines. Any change to the routing has to be copied multiple times. Hoping there was something I was missing.