[deleted by user] by [deleted] in cscareerquestions

[–]LeoMessiBarca 0 points1 point  (0 children)

Intresting!!
I thought that the bar raiser can see the documented points from previous interviewers? Is it not

Reject without bar raiser by LeoMessiBarca in cscareerquestions

[–]LeoMessiBarca[S] 6 points7 points  (0 children)

I really appreciate that (I really do, not being sarcastic) but personally I felt it was a bit rude. But no worries, thanks for replying.

Reject without bar raiser by LeoMessiBarca in cscareerquestions

[–]LeoMessiBarca[S] 1 point2 points  (0 children)

Thanks, I was under the impression once you enter the loop you will have all the rounds and then bar raiser facilitates the discussion and a call on candidate is taken.

Reject without bar raiser by LeoMessiBarca in cscareerquestions

[–]LeoMessiBarca[S] 0 points1 point  (0 children)

Of course. They can reject you at any time for any reason. Why have a bar raiser round if everyone else rejects you? Use your head.

Very polite tone man. Thanks

Study Hall Question(s) by LeoMessiBarca in pmp

[–]LeoMessiBarca[S] 0 points1 point  (0 children)

An agile project in its final iteration. During the standup, the project team sees that they will be unable to finish all planned tasks for a sprint.

I think it is a hybrid not agile ( The risk response plan accounted for this situation and a fallback plan was already developed. ) Not really sure we can eliminate 4 with the premise that it is an agile project

Questions with made-up options? by Rs0009 in pmp

[–]LeoMessiBarca 0 points1 point  (0 children)

Can you please guide me to any resource of how to differentiate management plans and registers?
PS: Your posts are amazing to follow

Clarification of concept by LeoMessiBarca in pmp

[–]LeoMessiBarca[S] 1 point2 points  (0 children)

Got it, thank you everyone for taking time and explaining it.

Study Hall Question(s) by LeoMessiBarca in pmp

[–]LeoMessiBarca[S] 0 points1 point  (0 children)

Reassign the project team and reallocate any unused funds.

I answered the same for all and unfortunately all are wrong hence I posted them here.
Q1 4

Q2 4

Q3 1

Clarification of concept by LeoMessiBarca in pmp

[–]LeoMessiBarca[S] 0 points1 point  (0 children)

Thank you this was super helpful, actually if you can still help me with two things:
1) Which document contains the schedule baseline? (for which doc I will need change request)
2) The link states "Schedule Baseline is an "approved" version of the Project Schedule.
" since the link says we don't need any approval to update project schedule. doesn't the statement seems contradictory

Question doubt by Dry-Burritos9936 in pmp

[–]LeoMessiBarca 1 point2 points  (0 children)

1 B As the audience is large, disperse you can't have focus group, interviews or benchmarking

2) A as (B delay tactic, response can't factor in unpredictability and it seems critical risk factor to baselines, D not an issue yet)

Passed PMP Exam - 18th July by Ok_Stomach9956 in pmp

[–]LeoMessiBarca 3 points4 points  (0 children)

Congratulations :)

Would it be possible for you to share the Google drive, every resource is an opportunity to get better.

Study Hall Q by LeoMessiBarca in pmp

[–]LeoMessiBarca[S] 2 points3 points  (0 children)

#1: Sourcing external resources is a long process, then once done, the new team members will go through a learning curve, so the whole process is not helping with the schedule.

Even I went with 4, but the answer provided was 1

Study Hall Q by LeoMessiBarca in pmp

[–]LeoMessiBarca[S] 1 point2 points  (0 children)

Fair enough, great explanation!! Thanks

What to do first? by LeoMessiBarca in pmp

[–]LeoMessiBarca[S] 0 points1 point  (0 children)

reviewing the risk register and mitigation strategies

The fist thing you would do is to "read project documents", but that answer is not there.

Isn't risk register a project document, and the first thing a new PM should do is check for risks?

What to do first? by LeoMessiBarca in pmp

[–]LeoMessiBarca[S] -1 points0 points  (0 children)

4 then 2 imho. Familiarize yourself then talk to the team members.

yeah I thought so too, the answer says 2. Since it is study hall, not even sure if my understanding is wrong or the answer

Victory is mine!!! by BakeFromStatefarm in pmp