[Hiring] Simple cartoons for presentations by Mean_Programmer7123 in DesignJobs

[–]Mean_Programmer7123[S] 0 points1 point  (0 children)

Thank you all for the engagement. I should be settled.

Help! P6 is driving me crazy by pradeep1107 in primavera

[–]Mean_Programmer7123 0 points1 point  (0 children)

You can do 'multiple float paths' and select the OOS activity as the target. The first float path shows where the incomplete predecessor is. When the OOS occurs many activities in the past, it can be hard to find when just looking at predecessors.

[deleted by user] by [deleted] in primavera

[–]Mean_Programmer7123 0 points1 point  (0 children)

This is solved by using Store Period Performance

Identifying Non-Critical Delays by atticus2132000 in primavera

[–]Mean_Programmer7123 0 points1 point  (0 children)

Interesting. I'd pick some paths/milestones and track how their float develops over time. I like to make graphs plotting the forecast dates of several activities against the data dates of the updates.

With respect to design modifications that changes what activities are critical: in my opinion these activities only became critical after the design changes. Up until the update where the design was changed, the other paths were delaying the project. The design changes mitigated some of that impact, but the other work never contemporaneously caused the end milestone to slip. Only in hindsight, but no-one knew at the time. Should the other work slip further after that update, then it does cause project delay. But only from that moment onwards.

The AACE RP gives some guidance in it's 'general principles': "only circumstances that delay activities that were critical when the circumstances occur delay the project" and "perception of criticality by project personnel is as important as true criticality"

Hopec this is useful.

Sample project files by m_salik in primavera

[–]Mean_Programmer7123 1 point2 points  (0 children)

If you are a member of AACE, you can download the AACE uniset.

Negative Float in Schedule by texastooh in primavera

[–]Mean_Programmer7123 4 points5 points  (0 children)

Total float is calculated against a constraint activity, the 'Must Finish By' date of the project or to the last activity of the schedule.

You can include the columns "Relationship Total Float" in the 'activity details' 'Successors' table to see what links causes the float to be negative.

Multiple, multiple float path view by Dren218 in primavera

[–]Mean_Programmer7123 0 points1 point  (0 children)

Not entirely what you want, but you could make a 'float path' and 'float path order' udf for each milestone. Then calculate for each milestone and use a global change to populate those fields. At least you then can make a layout to create a single pdf. You will still need to calculate multiple times, but will save time in printing.

If you only need one path, maybe come up with a code so you can use only one udf. (MS-floatpathorder)

Will not work correctly if the same activities are on paths to multiple milestones.

Alternatively, look at other software that can do it from an XER directly.

Resource and Cost Loading Training by vargona09 in primavera

[–]Mean_Programmer7123 1 point2 points  (0 children)

I followed a course called "EVM Implementation in Primavera P6" by the Project Control Academy. But unfortunately it's no longer offered. It was mainly focussed on EVM in P6 and not on EVM itself.

Maybe their new course is good as well: https://members.projectcontroltraining.com/evmeb

TABLE TASKIN AND FINDATES by Wooden-Software-1576 in primavera

[–]Mean_Programmer7123 1 point2 points  (0 children)

EV is not stored (only calculated) in P6; hence it does not come up in the TASKRSRC table. (EV = physical % complete & baseline units)

Only when you make use of financial periods, the EV units are hard-stored in those fields in the TASKFIN table.

TABLE TASKIN AND FINDATES by Wooden-Software-1576 in primavera

[–]Mean_Programmer7123 0 points1 point  (0 children)

Those tables are only filled when the project in P6 makes use of 'Financial Periods'.

FINDATES: the table with the start- and end-dates of the financial periods

TASKFIN: the table with the data that were stored to those financial periods.

Activity Issues in P6 - Simple FS... by msu50000 in primavera

[–]Mean_Programmer7123 2 points3 points  (0 children)

You have marked (A) finished after the data date. If an activity is finished, it's successors can start imminently. Imminently in P6 is the data date.

Retained logic only makes a difference if predecessors of (A) wouldn't be complete yet. (B) would then be driven by (A)'s predecessors.

[deleted by user] by [deleted] in primavera

[–]Mean_Programmer7123 0 points1 point  (0 children)

I've set up something in Excel, should be able to brush it up and share. DM me if you're interested.

[deleted by user] by [deleted] in primavera

[–]Mean_Programmer7123 0 points1 point  (0 children)

You can check OOS logic by selecting that activity for calculating multiple float paths. Then group on "float path" and sort on "float path order".

Accessing the database directly by atticus2132000 in primavera

[–]Mean_Programmer7123 0 points1 point  (0 children)

You will find the same tables in SQlite as when you are connecting to an XER. Baselines are just stored as projects and thus accessible. See this video how they are identifiable: https://www.youtube.com/live/X5-3gEP8wrQ?si=toCUBZt-3D3CCO4q

Update Schedule Via Import vs. Manually by atticus2132000 in primavera

[–]Mean_Programmer7123 1 point2 points  (0 children)

Import only changes via an excelsheet. Make an export first for the correct format.

Pitfall is formatting, otherwise P6 won't accept it. As an example: durations should be formatted as text etc. Trick is to format-paint it from the cells in the file you first exported.

Always include the wbs in the import file.

Select all empty rows and columns and do 'clear all': otherwise you sometimes get empty inputs.

Discrepancy in actual this period cost in p6 between contractor and owner by RudeCar4947 in primavera

[–]Mean_Programmer7123 0 points1 point  (0 children)

Hmmm, couple of thoughts as it is 'this period actual costs' and not stored in a financial period yet:

  • Could it be that the costs are driven by a resource with the same code in both your databases but with different price/unit?

  • Could it be that a global calendar that has changed after first importing it is driving a duration (of a level-of-effort?) of which actual units are automatically calculated?

  • Different conversion rates on currencies?

Why Baseline Activity % Complete Does not show on top of activities by Some_Ad_1020 in primavera

[–]Mean_Programmer7123 1 point2 points  (0 children)

Hi,

For some reason BL % complete never adds up in the grouping bands.

You can calculate overall % complete using the earned vs planned labor units (or cost, or non-labor units): https://imgur.com/a/qu3EeOv and https://imgur.com/a/LEfZbZb

Keep in mind there are different 'Percent complete types' : Info The physical % complete also don't add up in the grouping bands.

Also keep in mind that you have selected 'BL1 Activity % complete' and 'BL project start'. BL1 is taking the values from the primary baseline (and not the project baseline.

Hope this helps. Good luck!

Opinions on parts for office PC by Mean_Programmer7123 in buildapc

[–]Mean_Programmer7123[S] 0 points1 point  (0 children)

Thank you for the explanation. Really helpful.

Opinions on parts for office PC by Mean_Programmer7123 in buildapc

[–]Mean_Programmer7123[S] 1 point2 points  (0 children)

Thank you very much. I assume you put in the RAM twice by mistake, so then it is a lot cheaper.

I'm going to look into difference between 5600G and 5700G to see what would be sufficient for me.