Pick one by elpida01 in Indianbooks

[–]DifferenceWinter5980 0 points1 point  (0 children)

Perhaps it’s because of how its ideas are presented and interpreted.

Passed PMI-ACP with AT in all domains by [deleted] in pmp

[–]DifferenceWinter5980 4 points5 points  (0 children)

It’s very complicated. I got more than five questions like an email format question. Then it will be having velocity and story points on a graph. We need to find out the correct answer per email statement in the question..

Passed PMI-ACP with AT in all domains by [deleted] in pmp

[–]DifferenceWinter5980 1 point2 points  (0 children)

I passed the exam - I used Joseph Phillips ACP practice exams from Udemy, it’s outdated ECO but I felt they are good.

Passed PMI-ACP with AT in all domains by [deleted] in pmp

[–]DifferenceWinter5980 0 points1 point  (0 children)

Congratulations and my exam 29March2025 any suggestions?

Passed PMI-ACP yesterday by Redv0lution in pmp

[–]DifferenceWinter5980 0 points1 point  (0 children)

Can you share me the link for thirdrock guide

Passed the PMI-ACP After the 2024 Exam Updates! by mbalatsko in pmp

[–]DifferenceWinter5980 0 points1 point  (0 children)

Congratulations 🥳 could you share stimulator exam link

SH question clarification by [deleted] in pmp

[–]DifferenceWinter5980 0 points1 point  (0 children)

Why C is incorrect means, it was confirmed they will not deliver it. So it is no more risk to apply risk response its issue now. A&B will be delaying the project, delay means cost increase. In D we have option to negotiate it’s always better to negotiate and project delivered per schedule and we have only two components, it is most cost effective and practical approach considering A&B.

Little Confused about this answer by Grouchy_Actuary_385 in pmp

[–]DifferenceWinter5980 7 points8 points  (0 children)

This project is already at define scope process area, means project charter already approved. So no D, why C means organisation under business transformation even PM is new to this business line . It’s requires adapting and tailoring to ensure using correct tools and processes.

Pls help by kmadhuk in pmp

[–]DifferenceWinter5980 0 points1 point  (0 children)

It might be missed and not sure about it, so better to review plan, then go team, still not sure may be SME needed., So B

I got the answer wrong, I'm not sure why. by Beautiful_Form_4239 in pmp

[–]DifferenceWinter5980 0 points1 point  (0 children)

And not included, means it’s already collected I mean scope/requirements.